MAIN TASK OF PROJECT START-UP:
KOM | project procedure | risk assemntent | method statements | HSE Plan | Quality control plan | Welding book | Preparation of Job Cards and associated PTW (permit to work) | quantity assesment | level 4 schedule with CPA identification and S-CURVES defining the skill and quantity of work-force required (task ID CODE with the same Job Card number)| Final site logistic plan | Preparation of Job Cards and associated PTW (permit to work) | Site preparation: set-up of temporary offices, dressing rooms, mess area and warehouse | set-up of laydown areas fencing | delivery and placing of tools and containers areas fencing | installation of electrical panels at the work site | installation of pedestrian path (from TSF to work site) | unloading of materials at laydown/warehouse areas (scaffolding, insulation materials, bulk material from client, hydro-jet cleaning equipment, etc..)
MAIN TASK OF EXECUTION:
Daily toolbox meeting by the Project managment | LMRA before starts works on the work place | Staff schedule meeting (morning) to identify if any mitigation action are required | daily coordination meeting (post lunch time) to identify any SIMOPS and mitigate risks | Progress review daily meeting (Staff and Supervisor) | Schedule chasers will continuosly collect progress at site and report to planner | Quality control continuoselly inspection and reporting to Quality Manager | etc.. | see next slide focus on piping works
1 – ISOMETRICS RECEIVING: Isometrics spooling via spoolgen according to the priorities given by the site.
2 – PIPING BULK MATERIAL RECIVING: Material inspection report and segregated by material to avoid any potential contamination
3 – MATERIAL FEASIBILITY: Matching between isometric BoM and Bulk receive. Issue to fabrication also the relevant piping support.
3 – ISOMETRIC ISSUED FOR PREFABRICATION: Note that prefabrication of white and black material are not merged on same workshop
4 – PREFAFRICATION COMPLETE: As soon prefabricatiin is completed the eng dept prepares the as-built dwg to e checkek by QC
QUALITY CONTROLS
Dimensional inspection and NDT execution
RELEASE FOR PAITING
Shipping to painting workshop
PAINTING COMPLETE
As soon painting is completed the QC inspect quality of application
SHIPPING TO SITE
From SICIMONTAGGI workshop to site piping spools are shipped by truck.
1 – Constructability report
Constructability is made according Client engineering and materials deliverables and Client’s Key dates applying SICIMONTAGGI construction phylosofy based on HSE, Quality and schedule high standards.
2 – Definition of work package
Advanced Work Packaging construction projects that facilitates engineering planning to be driven by construction sequencing.
3 – MATERIAL FEASIBILITY
– Consist in matching:
– Foundation release
– Equipment delivery
– Steel structure delivered/released
– Piping Spools delivered
– Piping erection material delivered
3 – ERECTION ACTIVITIES
Equipment and Steel structures will be installed prior installation of piping, as soon steel structures and piping are relesed piping installation starts. NDT will be executed following daily production.
4 – TEST- REINSTATEMENT – PRE-COM
Till 60% of piping progress the erection will follow the principiple of WP, from 60% the erection will follow the principle of System completion.